Site Background

The PEC site was an industrial site located on a fluvial plain.   In 2001, Treatment Wall A was installed with a cut and fill excavation method. A bio-degradable slurry was used to maintain excavation trench stability. The 2001 Treatment Wall installation was believed to have achieved the design dimensions. In 2020, Treatment Wall A was rejuvenated using a caisson excavation method. The Wall A media typically consists of unconsolidated pea gravel with trace amounts sand and reactive media (compost, limestone and zero valent iron).

II. Project Scope

Original specification were the following for the new wall construction

Hoganas/Chemco have proposed to the selected contractor the use of the CLEANER PRB sponge iron that would bring great advantages as the wall was to be constructed BY VOLUME. The use of the sponge iron media brings a large mass differential against the qualified original ZVI material that was using a regrind iron from Connelly-GPM or Peerless. In addition, the Hoganas CLEANER PRB media shows higher purity (98 % + iron content), slower passivation, increased reactivity, longevity and surface area for more efficient contaminant reduction. However, due to the inherent morphology of all CleanER media – it will have higher surface area and longer life span than any other ZVI in environmental market.

Hoganas Environment Solutions maintains a state of the art laboratory facilities for process and product development work and customer/project support. Specific laboratories include soil/groundwater, microbiology, water and wastewater, and general analytical testing.

These service capabilities were used to help the contractor to determine ZVI quality and dosage rate during the construction of the PRB.

Calculated ZVI saving estimate using the CLEANER PRB Sponge iron

Over a volume of 1485 m3 @ 4 % v/v iron for M-1 wall this loading would represent a 59.4 m3 ZVI loading (or 59.4 m3 x 1.45 kg/m3) = 86.13 MT of CLEANER PRB

For the Connelly-GPM material using a density of 2402 kg/m3 you would require 59.4 m3 x 2.402 kg/m3 = 142.7 MT of regrind ZVI

III. Conclusions

  • Contractor was able to obtain significant budgetary and volume saving (media cost and freight) by using the CLEANER PRB sponge iron versus a typical regrind ZVI.
  • Lower density of the CLEANER PRB allow the ZVI to be better mix with the other component as it behave like sand in the mixing equipment giving a more homogeneous mix at the end.
  • Higher purity for the ZVI portion is providing the PRB with better longevity & reactivity.
Privacy Overview

This website uses cookies so that we can provide you with the best user experience possible. Cookie information is stored in your browser and performs functions such as recognising you when you return to our website and helping our team to understand which sections of the website you find most interesting and useful. More information on our Policies

Strictly Necessary Cookies

Cette option doit être activée à tout moment afin que nous puissions enregistrer vos préférences pour les réglages de cookie.

Show details Hide details
Analytics

This website uses Google Analytics to collect anonymous information such as the number of visitors to the site, and the most popular pages.

Keeping this cookie enabled helps us to improve our website.